Habshan 3 Stabilizer Feed Capacity Enhancement & Other Mechanical Works

Country:Abu Dhabi-UAE
Sector:UTILITIES AND OFFSITE FACILITIES
Client:ADNOC GAS
Start:January 2026
End:May 2027
Description:The project includes EPC activities for three packages for the HSGP (HABSHAN Sulphur Granulation Plant): Package-1: Install Bypass line & Downstream Isolation Valves for Deluge Skids in HSGP (HABSHAN Sulphur Granulation Plant) Package-2: Stabilizer Feed Capacity Enhancement in HABSHAN 1 / 2 (Piping Works for almost 3 km 16" and Pipe Rack Adequacy check) Package-3: HABSHAN 1 / 2 HAZOP & SIL Recommendations Implementations (ESD Valves Installations, Piping Works, Instrumentation, and Civil Works)..
Contract type:EPC